G'day Bluc,
Things are progressing but not quite as fast as anticipated.
Our glycol system for our fermenters and cold liquor tank is almost complete
Our steam boiler is about half way to being commisioned
We have nearly all the ancillary equipment as well, hoses, fittings, pumps etc
And we have had the frame go up for the tasting room, with electrical, plumbing, gyprock etc to follow on that side of the shed.